Business Case

Offshore project that we delivered from initiation stage to project completion.

1.

Project Title: Platform Installation Onboard Hilong 3000

Client: Husky CNOOC Madura Limited (HCML)

Background: Husky CNOOC Madura Limited (HCML) planned for Integrated Development of Madura Strait Block MDA & MBH gas reserves for sales gas to buyers in Java Island. The MDA gas field contains an estimated 300 bcf of gas, which can be produced using 5 (five) wells.



Job Scope: Platform installation support

No

task

structure

Remarks

1

Seabed Site Survey

MDA MBH

Survey reference, jacket deployment (upend) monitoring and           pile installation support

2

Jacket Lift-Off, Upending              and Setting Support

3

Jacket Post Setting  Support

4

Pile Installation Support

5

Jacket Levelling Support

6

GVI (General Visual Inspection)

2.

Project Title: PCP-MMF & LESA-KLB Pipeline Replacement Project

Background: The project is located offshore North West Java, approximately 120 km North-East of Jakarta. The project intends to maintain ONWJ base production as well as to get additional production. This project installed new pipelines and replaced existing sectional deteriorated pipelines during the year 2013 to 2017.

 

Job Scope:

NO

Task

1

ROV Site survey

2

GVI

3

Pipelaying support

4

Pipeline inspection

Structure: 14” Production PL from PCP to MMF Riser at PCP and MMF 10” Production PL from BG to BC Riser at BG and BC 6” Flexible pipeline from KKA to

KKNA J-tube at KKA and KKNA

Remarks: Pipelaying support, stinger check, profile check, touchdown monitoring survey reference, softline cutting

3.

Project Title: Sakhalin 2 Survey Inspection of Subsea Asset (SISA)

Client: Sakhalin Energy

Background: Sakhalin Energy Investment COMPANY Ltd. (further – COMPANY) is the operator of the Sakhalin-2 project under a Production Sharing Agreement with the Russian Federation. The Company was formed in 1994 to develop the Piltun-Astokhskoye oil field and Lunskoye gas field.

Job Scope:

NO

Task

1

GVI & CVI

2

Pipeline Chart Survey

3

Pipeline Inspection survey

 

Structure: Pipeline & Platform

Survey reference, pipeline survey, potential limited visibility due to shallow water and seabed soil

4.

Project Title: Rov Platform & Pipeline Installation Support

Client: Pertamina PHE WMO (PPW)

Background: PT. Pertamina Hulu Energi West Madura Offshore (PHE WMO) is a Production Sharing Contractor (PSC) of SKK Migas. It produces more than 20,000 BOPD and 100 MMSCFD. All gas produced from this block will be compressed for customers.

Job Scope: 

NO

TASK

1

ROV Site Survey

2

GVI

3

Seabed Survey

4

Installation Support

Structure: CPP2, PHE-12, PHE-24, Riser

Survey reference,   flood   valve   inspection,

jacket deployment (upend) monitoring

5.

Project Title: Provision of Special Periodical Survey Underwater Inspection In-Lieu of Dry Docking (UWILD)

Client: Bermuda (M) Sdn. Bhd

Background: A floating production storage and offloading SEPAT (FPSO) unit is a floating vessel used by the offshore oil and gas industry to store oil. FPSOs are preferred in frontier offshore regions as they are easy to install and do not require a local pipeline infrastructure.